Concrete now on floors

Posted By: UT Medical Center
02/14/2012

For the next two to three weeks we will continue to see the same activity on site. However, the steel structure is in place on the eastern half of the building and concrete slabs have been placed on the upper east floors. Also, slab plumbing rough-in has started and will continue through this month. 

The steel structure on the west floors will continue to be completed during the next two weeks. 

New Developments: Metal studs for the eastern exterior wall of the building should start this week!